New home construction in Massachusetts follows a set order: permit, site and foundation, framing, rough inspections, insulation, finishes and the final. Knowing what happens at each stage, and what has to be right before the next one starts, is the best protection a first-time builder has.
Permit and plan review with the town building department
Every new house starts at the building department of the town or city where it will stand. The plans, a plot plan showing where the house sits on the lot and the supporting documents go in with the permit application. The building official reviews them against the Massachusetts State Building Code, 780 CMR, and zoning rules such as setbacks and height limits are checked as well.
Other approvals often have to come first or alongside. A lot without town sewer needs a septic design under Title 5, which typically involves soil testing and approval through the local board of health. A lot near wetlands may need a conservation commission review. A lot inside a local historic district may need that commission to look at the exterior. Which of these apply depends entirely on your lot and your town, and we sort that out with you at the start.
Steve holds an unrestricted Massachusetts Construction Supervisor License, and the permit is pulled under it. That makes him the person responsible to the building department for the work, and the person the inspector deals with until the final.
Plan review takes time, and how long varies a lot from town to town. We submit a complete package so the review is not held up by missing paperwork, and we tell you when it goes in and when it comes back.
Site work, excavation and footings below frost
Once the permit is issued, the house gets staked out on the lot, the area is cleared where needed and the hole is dug for the foundation. Massachusetts ground is not always cooperative. Ledge, boulders, high groundwater and fill from an old structure all turn up, and excavation is where you find out. If it happens, we stop, show you what we found and talk through the options before going further.
Footings go below frost depth, commonly about four feet in Massachusetts, so the ground freezing and thawing each winter does not heave the house. The footings are typically inspected before concrete is placed. Foundation walls follow, then damp-proofing or waterproofing on the outside, drainage at the footing and backfill. A good foundation is one you never think about again, and the only way to get one is to get this stage right.
We also confirm before digging how the house will get water and send away wastewater, either at the street or through a well and septic system on the lot. Those runs decide where the foundation openings go and when the trenches are dug, and planning them now saves tearing up a finished yard later.
Framing and the rough inspections
Framing is when the house starts to look like a house, and it moves quickly. The sill goes down on the foundation, then floor systems, walls, the roof, sheathing and the weather barrier. Windows and exterior doors usually go in during or right after this stage, with flashing installed so any water that gets behind the siding is sent back out rather than into the wall.
With the frame up and the house dried in, the licensed electricians and plumbers do their rough-in, along with the heating and cooling work. Then come the rough inspections. Framing, electrical and plumbing are each checked by the inspector responsible for that work, and nothing gets covered until they are signed off.
This is also the best time for you to walk the house. Rooms you have only seen on paper are now real spaces you can stand in. If a window feels wrong or an outlet is in the wrong place, this is when moving it is simple. Any change gets written up and priced before it is made.
Roofing goes on as soon as the frame allows, with ice and water barrier at the eaves and in the valleys. A house left open to a few weeks of New England rain takes on moisture that has to dry out before the walls are closed.
Insulation, air sealing and the energy code
After the rough inspections, the walls and roof get insulated and the house is air sealed. Massachusetts energy requirements are part of the building code, and many towns have adopted the stretch energy code, which sets a higher bar. Depending on your town, that can mean testing how airtight the house is before it is finished.
Insulation is typically inspected before drywall goes up. It is easy to install poorly. Gaps at corners, batts crushed behind wiring and unsealed holes at the top of the walls all disappear once the drywall goes on, but you feel them every winter as drafts, cold rooms and higher heating bills. We check it before the inspector does, because the inspector sees it for a few minutes and you live with it for decades.
Ventilation belongs to the same stage. A tight house needs fresh air brought in on purpose, so mechanical ventilation is planned along with the heating and cooling. The energy code also covers windows, the foundation and the attic, and each piece has to hold up its end.
Finishes, the final inspection and moving in
Drywall, interior trim, cabinets, tile, flooring, paint and fixtures follow, roughly in that order, with some overlap. Outside, the siding, trim, gutters, driveway and final grading are finished. The licensed trades come back to set fixtures, devices and equipment.
When everything is complete, the building department does a final inspection, and once the house passes, the town issues a certificate of occupancy. You can move in only after that. Before the final, you and Steve walk the house together room by room. Anything not finished to the standard you agreed on goes on a list, and the list gets closed out.
Through all of it you get regular updates from Steve on what got done, what is next and what decisions are coming up. A first house is a lot to keep track of, and you should never have to guess where yours stands.
Your selections fit in here too. Cabinets, tile, flooring and fixtures have to be chosen and ordered well before they are needed on site, so we go over that list with you early and remind you as each deadline comes up.
See the rest of our homes work, or browse the gallery for rooms we have finished.
How the job runs
Homes work follows the same order every time, so you always know which part of the job you are in.
- First
A walkthrough comes first, with Steve, at the house. You show him the problem and the wish list; he shows you what the structure and the systems will allow.
- Then
The proposal is written down in plain words. If a decision is still open, it says so, and it says when we need it from you.
- During
Permits are pulled, the work is scheduled, and you hear from us as it moves. If something unexpected turns up, you hear about it before anything changes.
- Last
A final walkthrough with Steve closes the job. You go room by room and nothing is called finished until you agree it is.
Questions people ask about new home construction
What inspections does a new house go through in Massachusetts?
Typically footings, rough framing, rough electrical and plumbing, insulation and a final, though the exact list depends on your town. The licensed trades are inspected for their own work. Nothing is covered until the relevant inspection has passed.
Why do footings have to go so deep?
They have to sit below frost depth, commonly about four feet in Massachusetts. Ground that freezes and thaws moves, and a footing above that line can heave and crack the house above it.
Do I need a septic system?
Only if your lot is not on town sewer. If it needs one, the system is designed under Title 5 and usually approved through the local board of health after soil testing, and that work has to happen early.
When can I make changes to the layout?
The easiest time is on paper, and the next best is during framing, before anything is covered. Every change is written up and priced before it is made, so you know what it does before you decide.
What is a certificate of occupancy?
It is the town's sign-off that the house has passed its final inspection and can be lived in. You move in after it is issued, not before.
More homes work
Custom Home Design-Build
Custom home design-build puts the drawings and the construction of your house under one contract.
Modern Home Construction
Modern home construction strips a house down to clean planes, large glass and very little trim.
Contemporary Home Construction
A contemporary home pairs current design with shapes New England already knows: open plans under pitched roofs, mixed cladding and bigger windows in a familiar form.
Estate Home Construction
Estate home construction covers the whole property, not only the main house: wings, detached garages, guest quarters, long driveways, heavy site work and septic design.
High-End Home Construction
High-end home construction is about how the work gets checked, protected and recorded while the house goes up.
New Construction Homes
A new construction home gives you current code, current insulation and a layout you chose, in place of the surprises an older New England house keeps behind its plaster.
Tell Steve what you have in mind
Monday to Friday 7 to 5, Saturday 8 to noon. Based in Raynham and working within about a hundred miles of it. See finished rooms in the gallery.